• JUNE 2024
Divider Line Element
  • We had left the original Mikvah ​up for as long as possible for ​community use. It was the final ​part of the original building to ​be taken down this past ​month.
  • The pilings are nearly ​complete and cement mixers ​have arrived and have started ​pouring cement.


  • APRIL 2024
Divider Line Element
  • Construction now focuses on ​completing the piling work, ​creating strong and safe ​foundational walls for the ​building.


  • FEBRUARY 2024
Divider Line Element
  • Started the underground retaining wall work
  • Lots of digging onsite


  • JANUARY 2023
  • Land Department visited to mark the precise boundaries of the land.
  • Received 30 tons of reinforcement bars for piling (to create strong walls for the foundation).
  • A surveyor team also created a site layout, using the exact marked points provided by the Land Department.
  • Lots of digging onsit